Red and yellow alerts were issued over the Visayas grid on Tuesday, Nov. 24.
The National Grid Corporation of the Philippines said the red alert -- which is raised when power supply is not enough to consumer demand -- is in effect from 5 to 6 p.m.
The yellow alert -- which denotes the operating margin is insufficient to meet the transmission grid's contingency requirement -- is up from 3 p.m. to 5 p.m. and 6 to 9 p.m.
The NGCP said available capacity is 2501 MWs and peak demand was at 2519 MW.m