The Visayas grid was placed under a yellow alert on Friday, Nov. 27.
The National Grid Corporation of the Philippines said the alert is in effect from 5 p.m. to 6 p.m.
A yellow alert is raised when the operating margin is not enough to meet the transmission grid's contingency requirement.
According to the NGCP, the hoisting of the alert was due to the unavailability of TVI-2 and the derated capacity of TVI-1.
The unavailability of PCPC and KSPC Unit 2 and the limited power import from the Mindanao grid were also cited as factors that contributed to the declaration.
Available capacity is at 2500 MW.
Peak demand, meanwhile, is at 2428 MW, the NGCP said.